If you are building, or buying a home that will be built, under the Future Homes Standard, the heating has to be settled well before the plans are fixed. The standard is not a list of approved appliances; it is a performance target for the whole home, and the heating system decides more than anything whether a design meets it.
The standard was published in March 2026 and applies from 24 March 2027. This guide covers what it means for heating, which routes are realistic, how to tell whether your site falls under the old or new rules, and what to ask before you commit. For the standard as a whole, see the Future Homes Standard explained.
The Future Homes Standard and your heating in short
- It applies to new homes in England from 24 March 2027. Wales and Scotland have their own rules.
- It is a performance target, not a list of appliances, but the target is now based on a heat pump, so gas boilers cannot realistically pass.
- Older applications can still use the 2021 rules if they went in before 24 March 2027 and work on each home starts by 24 March 2028.
- Settle four things at design stage: hot water, flow temperature, cylinder space and the outdoor unit position.
- New houses also need solar panels under a new requirement, which changes how the heating is costed and run.
What the Future Homes Standard changes about heating, in plain terms
The Future Homes Standard tightens the building regulations for new homes in England. Wales, Scotland and Northern Ireland set their own rules, so check those if your site is outside England.
Standard published: new Approved Documents L and F
In force for new homes in England
Last date for older applications to have started work on each home
The standard sets targets for the finished home, and an energy assessor calculates whether the design meets them. Fabric, ventilation, solar panels and heating all feed the same calculation, and a weak element in one place has to be made up elsewhere. Under the 2021 rules a well-insulated house with a gas boiler could pass. The new targets assume a heat pump.
| Part of the design | What the standard expects | What it means for heating |
|---|---|---|
| Target | Energy, carbon and fabric targets for the whole home, set by a reference design with a heat pump | A gas-heated design starts from far behind |
| Heating fuel | Carbon and primary energy factors no higher than grid electricity | Mains gas as the main fuel cannot meet it |
| Solar panels | New requirement for on-site generation; for houses, sized from 40% of the ground floor area | Daytime power that a heat pump and cylinder can use |
| Fabric and air | Better insulation and airtightness, with the reference design using waste water heat recovery | Lower heat loss, so a smaller heat pump |
| Calculation | SAP 10.3 at launch; the new Home Energy Model has been delayed | Ask your assessor which method and version they used |
Summary of the published standard for England. Exemptions apply, for example where panels could not generate a minimum output. Check Approved Document L itself, which is what building control will check.
Why gas boilers are effectively out for new homes, and what replaces them
Gas boilers are not banned by name. But with the target built around a heat pump, and the heating fuel limited to the carbon level of grid electricity, a gas boiler as the main heat source cannot realistically pass. A scheme that relies on one is designing against the standard from the first drawing.

Dropping gas also removes the cost of a gas connection to each plot. On a scheme of any size, ask your designer to compare the whole installed cost of each route, including the connection charges you no longer pay, rather than the cost of the heat source alone.
Heat pumps, hybrid and direct electric: which routes are realistic
For most houses a heat pump is the realistic route. Whether air or ground source suits your plot is covered in air source or ground source for a new build, so I will not repeat it here.
| Route | Best suited to | Likely to pass? | Watch out for |
|---|---|---|---|
| Air source heat pump with cylinder | Most houses of any size | Yes; it is the basis of the target | Emitter sizing, cylinder space, outdoor unit position |
| Ground source heat pump | Larger plots and self-builds with groundwork planned | Yes, often with higher efficiency | Cost and programme time of the ground loop |
| Heat network | Larger urban schemes | Yes, if the network is low carbon | Tariff, standing charge, and who fixes the plant |
| Direct electric with a hot water heat pump | Small, very well insulated flats | Possibly, with extra fabric or solar | Higher running cost per unit of heat |
| Hybrid (heat pump plus gas boiler) | Rarely a good fit for a new home | Unlikely; ask your assessor to model it first | Two systems to fit, service and explain, plus a gas connection |
Buyers see the energy rating and running costs, so running cost matters as well as passing. My comparison of ten years of heat pump and gas boiler running costs shows why.
Will your site fall under the old rules or the new? How to check
Not every home finished after March 2027 will be built to the new standard. The published transitional arrangements are:
Older applications
- A building notice, initial notice or full plans application went in before 24 March 2027
- Work on the home has started by 24 March 2028
- “Started” means more than foundations: the ground floor structure must be in place
Everything else
- Applications made on or after 24 March 2027
- Homes on older applications where work has not started in time
- Plots still relying on older transitional rules from 2013 or 2021, which have been withdrawn, if work has not begun
Gather these facts before you plan the heating:
- The application date, what type it was, and whether it covers the whole site or some phases only.
- Whether work has started on each home, to the point the regulations count as a start. On a phased site, later plots can miss the date even when the application covers them.
- Which version of the regulations the design-stage energy calculation was done against.
- Whether the plot has been redesigned since. Ask building control whether a significant change, including a switch of heating system, affects the position.
Ask building control or your approved inspector to confirm the position in writing, plot by plot on a phased scheme. Do not plan around a position you have not confirmed: if the start slips past March 2028, the heating may have to change after the design is fixed, which is the most expensive time to change it.
Self-builders will find a timeline in self-build heating before the Future Homes Standard starts. Buyers should ask the developer in writing which rules apply to their plot.
Heating decisions to lock in at design stage, not at first fix
By first fix, the pipe routes, cylinder location and electrical supply have usually been decided, and changing the heating means changing the building around it. Settle these four at design stage:
Hot water
A heat pump heats a cylinder, and in a well-insulated home hot water is a large share of the energy used. Confirm the size against bedrooms and bathrooms, and how the cylinder is heated for regular disinfection, and what that costs.
Flow temperature
The reference design assumes 45°C; aim for 35°C to 45°C, with underfloor heating or larger radiators sized to deliver the heat at that temperature. A higher flow temperature to keep radiators small means more electricity than the calculation shows.
Cylinder space
A cupboard drawn for a combi boiler is too small. Allow for the cylinder’s size, a drain nearby, service access and a short pipe run to the heat pump.
Outdoor unit
Fix its position on the plans, not on installation day: clear airflow, a short pipe run, and noise kept away from bedrooms and the neighbours’ windows.

For the emitter choice, see underfloor heating or radiators with a heat pump. For cylinders, see the best hot water cylinders for heat pumps, and whether you also need a buffer, do you need a buffer tank? For siting the unit, see how loud is a heat pump?

Ventilation and heating need designing together. Tighter new homes usually have mechanical ventilation; see MVHR and a heat pump in the same house. And because new houses now need solar panels, ask how the heat pump and cylinder will use the daytime surplus: will your solar panels run your heat pump?
What it means for build cost, and the questions to put to your M&E designer
| Cost item | Compared with a gas design |
|---|---|
| Heat pump and cylinder, installed | More than a boiler and a small cylinder or none |
| Emitters sized for low flow temperatures | Larger radiators or underfloor heating |
| Electrical supply and consumer unit | May need more capacity; ask the network operator early |
| Gas connection and gas pipework | Saved altogether |
| Solar panels | Now required on most new houses whatever the heating |
| Extra fabric to pass the calculation | Less needed when the heating matches the target |
I have not given a total because it varies too much with house size, fabric and system. Ask your designer to compare whole installed costs, not just the heat source.
Questions for your mechanical and electrical (M&E) designer:
- Which regulations, and which calculation method and version, is this design assessed against?
- What design flow temperature have you used, and are the emitters sized for it?
- What seasonal efficiency do you expect from the heat pump, and on what assumptions?
- How big is the cylinder, where does it go, and how long is the pipe run to the heat pump?
- Where does the outdoor unit sit, and what is the noise at the nearest window?
- Is the electrical supply big enough, and has the network operator been asked?
- If the fabric or ventilation changes, does the heating design have to change too?
For a second opinion before you sign, see is your heat pump design right?
What a buyer or self-builder should ask for on a new home
Buyers do not choose the heating, but you can ask what has been specified and how it is documented. Self-builders can ask the same of their designer and installer. Take this list along:
- Which building regulations apply to the plot, confirmed in writing
- The design-stage energy assessment and predicted rating
- Make, model and size of the heat pump and cylinder
- Design flow temperature and the room-by-room emitter schedule
- Outdoor unit position and expected noise at the boundary
- Solar panel size, and whether the heat pump or cylinder uses the surplus
- Warranty terms, and who services the system
- The commissioning certificate and a handover of the controls
- Expected running cost, with the assumptions stated
- For heat networks: the tariff, standing charge and maintenance arrangements
An installer’s quote should state all of this. Print my heat pump quote checklist to compare quotes line by line, and read buying a new-build home with a heat pump for what living with one is like.
Common questions
The Future Homes Standard and heating: common questions
Are gas boilers banned in new homes from 2027?
Not by name. But the target is based on a heat pump and the heating fuel must be no more carbon-intensive than grid electricity, so in practice a gas boiler as the main heat source cannot pass in England.
When does the Future Homes Standard start?
It was published on 24 March 2026 and applies from 24 March 2027. Homes on applications made before then can follow the 2021 rules if work on each one starts by 24 March 2028.
Does it apply to extensions or my existing home?
No. It covers new homes. Extensions and work on existing homes follow their own Part L requirements, which do not force a heat pump.
Does it apply in Wales or Scotland?
No. Wales sets its own building regulations, and Scotland’s New Build Heat Standard has already ruled out direct-emission heating such as gas boilers in most new homes since April 2024.
Do new homes need solar panels?
New houses in England generally need solar panels sized from 40% of the ground floor area, with exemptions where they could not produce a minimum output. See solar PV on new builds.
Can a new home still use direct electric heating?
Possibly in a small, very well insulated flat, often with a hot water heat pump and extra fabric or solar. It costs more to run per unit of heat than a heat pump, so check the running cost as well as the pass.
Next step
Planning a self-build or a small scheme? Ask for a quote through my heat pump quote page, with your plans and the date your building regulations application went in.